Link between estimates and projects

Gilles Van Handenhove's Avatar

Gilles Van Handenhove

11 Dec, 2013 03:25 PM

Hello there,

A question about the links between estimates and projects:

When a project is created from an estimate, it automatically includes all tasks listed in the estimate.

Now, if the estimate is modified and additional tasks are created, the project doesn't seem to be updated with the extra tasks and time allocated to them.

So the analysis of the time spent on the project vs. the estimated time does not work.

Is there a way to resolve this problem?

Thanks in advance for your response.

Best,

Gilles Van Handenhove
Project Manager
And we are

Base

www.basedesign.com
www.basenow.net

T +32 2 226 40 47
M +32 488 255 427
[email blocked]
---------------------------------
BaseBRU
Chaussée de Forest 62/ 5
1060 Brussels / Belgium

  1. Support Staff 1 Posted by Seth B on 11 Dec, 2013 05:21 PM

    Seth B's Avatar

    Hi Gilles,

    When you create a project from an estimate, it copies all tasks over.

    You have 3 options here.

    1. Don't modify your estimates after the fact
    2. Manually re-create the added tasks in the project
    3. Delete & re-create the project from your estimate

Reply to this discussion

Internal reply

Formatting help / Preview (switch to plain text) No formatting (switch to Markdown)

Attaching KB article:

»

Attached Files

You can attach files up to 10MB

If you don't have an account yet, we need to confirm you're human and not a machine trying to post spam.

Keyboard shortcuts

Generic

? Show this help
ESC Blurs the current field

Comment Form

r Focus the comment reply box
^ + ↩ Submit the comment

You can use Command ⌘ instead of Control ^ on Mac